18 Ocean Drive

Posted on: Apr 12, 2013

Louis J. and Saralynn Vollmer
04/11/13 – Received application for constrution permit and set of plans by email for NEW HOUSE. There will be pile driving
04/15/13 – Architecural Review Head recommended approval upon reciept of large copy of revisedplans, fee, and site plan showing placement as discussed with architect
04/17/13 -Revised large plans and fee delivered to North Shores office. Requested revised plans by email from architect
04/18/13 – Emailed PDF of revised plans received
04/18/13 – Comment deadline letter prepared to go to neighbors. Sent
04/23/13 – TEST PILING. Approved by board
05/02/13 – Comment deadline
05/02/13 – Board voted to Approve subject to conditions.Approval letter sentwith conditions
06/14/13 – Board received notice that Vollmers have changed builders from Echelon to Burton Builders, Inc. Notice was sent to contiguous neighbors