21 Robins Lane

Posted on: Sep 06, 2012

Helen Hoart and Bailey Starrett
08/25/12 – Application received by email for new house
08/27/12 – Plans received
08/28/12 – Asked to disregard plans by owner, due to miscalculations. Revised plans to come shortly
09/18/12 – Deconstruction of current house to begin
09/17/12 – Revised Plans received in North Shores office, large hard copy and by email PDF
09/19/12 – All correct plans received in office and by Architectural review
09/20/12 – Plans sent to neighbors for comments
10/04/12 – Comment deadline date
10/05/12 – expected pile driving to begin
10/16/12 – Plans voted on and approved by the Board upon conditions relating to 1st floor elevation, setback requirements, drainage, placement of AC compressor units, and visual screening.