33 Holly Road
Yvonne and Bill Russell
08/02/11 – Plans for new house and application form for construction permit were turned in to the office and by email attachment
08/03/11 – Hard copies of plans submitted
08/04/11 – Architectural Review reported that the floor area shown on the plans exceeds amount allowed by covenants
08/05/11 – Architectural Review Report forwarded to Russells by email
08/17/11 – Comment Deadline date
08/18/11 – Revised plans received
08/18/11 – More info requested by Architectural Review Head
08/24/11 – Additional info submitted
08/31/11 – Architectural Review Head recommends approval.
09/03/11 – Approved: Pile driving scheduled to begin: September 13, 2011